Project Overview

Project: Coventry Railway Station
Area: 3,500 m²
Completion Date: August 2006
Contractor: James M Green, Birmingham
Client: Network Rail
Main Contractor: Galliford Try
System: Profiles System

download pdfDownload this case study

Background

Coventry-Railway-Station-02Coventry railway station in the West Midlands, which was originally built in 1840, is on the Birmingham loop of the West Coast Main line with four trains an hour passing through on the way to London Euston. The current station was completed in 1962 and is now a grade II listed building.

A major project of essential works in and around the station was underway by Galliford Try and this included the refurbishment of trackside and platform roofs.

Challenge

The existing built-up roof waterproofing was in such poor condition that water was ponding and penetrating the building. Splits were evident in the perimeter details which had been caused by differential movement in the aluminium edge trim.

James M Green had to cope with roofs sited underneath power cables which could only be worked on at night with limited access and limited scaffold space. All personnel on the project had to undergo two days of Personal Trackside Safety Training to prepare them to work alongside 25,000 volts of electricity in limited lighting conditions.

Solution

Coventry-Railway-Station-03Network Rail wouldn't allow stripping of the existing roof as it would take too long, and so the Profiles system was chosen so they could overlay the existing roofs easily in floodlit conditions.

James M Green applied the new Profiles torch-on warm roof system, which included Icopal Thermazone insulation to meet required u-value standards and was topped with FireSmart Profiles XL capsheet.

Parapet details were treated with Icopal’s Antrim GRP edge trims and the totally integrated roofing specification also included Icopal Roofguard Outlets, Telescopic Vent covers. The Profiles system is an engineered elastomeric bitumen waterproofing system supported by a 20 insured guarantee. Materials were supplied on a like-for-like basis to comply with the limitations imposed by the station's listed status.

Teams of eight roofers worked in 12 hour shifts, 7 days a week to complete the job, which was finished ahead of schedule at the beginning of August; completed in just one month. 

    Contact Icopal 0161 8654444

    Find Local Support

    To discuss your project in more detail please contact
    Your Local Area Manager

     

    Technical Support

    Telephone:

    0330 123 4585

    Email: technical.uk@bmigroup.com

     

    Sales Enquiries & Orders

    Telephone:

    0843 224 7400

    Fax:

    0843 224 7401

    Email: sales.admin@bmigroup.com

    Latest News

    BMI’s apprentice competition demonstrates its commitment to roofing’s future

    Read more...

    BMI UK & Ireland launches to the UK construction industry

    Read more...

    BMI hosts a meeting of minds

    Read more...

    BMI Building Futures For Veterans

    Read more...

    The Best From The West

    Read more...

    Hot melt provides great result for sports area

    Read more...

    This site uses cookies in accordance with our Website Privacy Policy. By continuing to browse the site you are agreeing to our use of cookies. To browse without the use of cookies, you can opt-out as explained in our Website Privacy Policy or adjust your cookie settings for your browser

    Icopal: We Protect Your Building