Project Overview

Project: Watford Colosseum, Hertfordshire.
Area: 1,000 m²
Completion Date: April 2011.
Contractor: McCormick Flat Roofing Ltd, Hornchurch
Client: Watford County Council
Main Contractor: Kier London Ltd
System: Elastoflex Liquid Applied Waterproofing

download pdfDownload this case study

Background

ICS1034-Watford-Colosseum-Hertfordshire_380x265The Grade II listed art-deco building which was built in 1938 has recently completed a £5.5 million refurbishment including a new entrance and foyer and cafe area.

The roof had been leaking badly for years and numerous repairs had been carried out. In fact, the leaks were at times so severe that 'wheelie' bins had been used to catch the water. The metal roof itself formed a mansard type roof to the steep sided slated roofs.

Challenge

As part of the refurbishment works, a new copper roof to match the existing was originally specified, however due to heavy budget restraints the main contractor asked McCormick Flat Roofing Ltd to come up with a more cost effective alternative solution, whilst giving the same high level of waterproof integrity. The main contractor also did not want to go to the trouble or cost of erecting a temporary roof.

McCormick Flat Roofing therefore proposed the following;
To fully prepare the existing copper roof to bring it to a sound and stable condition. The existing copper roof had been completely covered in bituminous paint and subsequently overcoated with solar-reflective paint. This was all stabilised and removed where it had been delaminated.

Solution

This was then coated in Elastoflex Primer, with bond tests carried out to ensure adhesion. This was then followed by the Elastoflex liquid waterproofing system, comprising a base layer, reinforcing fleece and top coat, all laid wet-on-wet to ensure full adhesion of the waterproofing layers, and as it is fluid applied, the system is seamless and thus removes the risk of lap failure. The system was carried over the ridge tile of the traditional slate finished side roofs to ensure that new roof was completely weather-tight. The 1000m² roof is now complete and leak-free

 

    Contact Icopal 0161 8654444

    Find Local Support

    To discuss your project in more detail please contact
    Your Local Area Manager

     

    Technical Support

    Telephone:

    0330 123 4585

    Email: technical.uk@bmigroup.com

     

    Sales Enquiries & Orders

    Telephone:

    0843 224 7400

    Fax:

    0843 224 7401

    Email: sales.admin@bmigroup.com

    Latest News

    BMI’s apprentice competition demonstrates its commitment to roofing’s future

    Read more...

    BMI UK & Ireland launches to the UK construction industry

    Read more...

    BMI hosts a meeting of minds

    Read more...

    BMI Building Futures For Veterans

    Read more...

    The Best From The West

    Read more...

    Hot melt provides great result for sports area

    Read more...

    This site uses cookies in accordance with our Website Privacy Policy. By continuing to browse the site you are agreeing to our use of cookies. To browse without the use of cookies, you can opt-out as explained in our Website Privacy Policy or adjust your cookie settings for your browser

    Icopal: We Protect Your Building